Blog

Education Edge PMP PMBOK Week 4 Office Read – Cost Knowledge Area

Education Edge · October 25, 2016 · 5 min read

Cost Management Knowledge Area:

 Project Cost Management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget. Project Cost Management is primarily concerned with the cost of the resources needed to complete project activities. The knowledge area of Project Cost Management consists of the following four processes: 
Process NameProject Management Process GroupKey Deliverables
Plan Cost ManagementPlanningCost management Plan
Estimate Costs PlanningActivity Cost Estimates, Basis of Estimates
Determine Budget PlanningCost Baseline
Control CostsMonitoring and ControllingWork Performance Information
 Plan Cost Management process establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. Cost management plan includes:·       Units of measure·       Level of precision·       Level of accuracy·       Organizational procedures links·       Control thresholds·       Rules of performance measurement The Inputs, Tools and Techniques and Output of Plan Cost Management process are given below: 
Project Management PlanExpert JudgmentCost Management Plan
Project CharterAnalytical Techniques 
Enterprise Environmental FactorsMeetings 
Organizational Process Assets  
 Estimate Costsis the process of developing an approximation of funds needed to complete project activities. The project in the initiation phase has a rough order of magnitude (ROM) -25% to +75% Later with more information is knows, definitive estimates could narrow the range of accuracy to -5% to +10% Direct Costs are attributed directly to the project work and cannot be shared among projects (wages, material, equipment, etc.). Indirect Costs are overhead costs that incurred for the benefit of more than one project (taxes, training, software licenses etc.). Variable Costs vary depending on the amount of work or production (cost of materials, supplies, wages, etc.). Fixed Costs remain constant throughout the project (cost of office setup, rentals, etc.). Cost of quality includes all costs incurred over the life of the product. Contingency Reserves are used for known risks, which are specifically identified risks. Management Reserves are used to accommodate unknown risks, or unidentified risks. Rolling Wave is a common technique used to estimate high-risk projects. The Inputs, Tools and Techniques and Output of Estimate Costs process are given below: 
Cost Management PlanExpert JudgmentActivity Cost Estimates
Human Resource Management PlanAnalogous EstimatingBasis of Estimates
Scope BaselineParametric EstimatingProject Documents updates
Project ScheduleBottom-up Estimating  
Risk RegisterThree-Point Estimating  
Enterprise Environmental FactorsReserve Analysis 
Organizational Process AssetsCost of Quality 
 Project Management Software 
 Vendor Bid Analysis 
 Group Decision Making Techniques 
 Determine Budgetis the process of aggregating the estimated cost of individual activities or work packages to establish an authorized cost baseline. The cost baseline is the approved version of the time-phased project budget. Cost baseline includes all authorized budgets, but excludes management reserves. Cost baseline can only be changed through formal change control procedures. Project Cost performance will be measured against the authorized budget. Cost estimates are aggregated by work packages in accordance with the WBS. The expenditure of funds should be reconciled with any funding limits on the commitment of funds for the project. Total funding requirementsand periodic funding requirements (e.g., quarterly, annually) are derived from the cost baseline.     The Inputs, Tools and Techniques and Output of Determine Budget process are given below: 
Cost Management PlanCost AggregationCost Baseline
Scope BaselineReserve AnalysisProject Funding Requirements
Activity Cost EstimatesExpert JudgmentProject Documents updates
Basis of EstimatesHistorical Relationships 
Project ScheduleFunding Limit Reconciliation  
Resource Calendars  
Risk Register  
Agreements  
Organizational Process Assets  
 Control Costis the process of monitoring status of the project to update the project budget and managing changes to the cost baseline. Monitoring cost performance to isolate and understand variances from the approved cost baseline. Cost baseline compared with actual results. Project cost controls seeks out the causes of positive and negative variances and is part of the Perform Integrated Change Control process Earned value management (EVM) is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress. Forecasting involves making projections of conditions and events in the project’s future based on current performance information and other knowledge available at the time of the forecast. To-Complete Performance Index (TCPI) is a measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal. AC is the actual cost incurred Earned Value EVvalue of the work actually accomplished Planned Value (PV)is the value of the work planned to be done. CPI refers to Cost Performance Index. It is defined as CPI = EV/AC (If CPI is less than 1, this means that the project is over budget). SPI refers to Schedule Performance Index. It is defined as SPI = EV/PV Budget at Completion (BAC)funds you have BUDGETED for the total Job. EAC = BAC/CPI Estimate at Complete (EAC)current total expectation of project cost.  Estimate to Complete (ETC)from now on, how much MORE do we expect it to cost to finish the project.ETC = EAC – AC Variance at Completion (VAC)how much over or under budget do we expect it to be. VAC = BAC – EAC The calculated CV, SV, CPI, SPI, TCPI, and VAC values for WBS components, in particular the work packages and control accounts, are documented and communicated to stakeholders. If the schedule is inflexible, then the only possible tradeoffs available to the project manager may be cost versus quality. The following will help you answer over 8 questions on the exam: 1.       CV = EV – AC2.       SV = EV – PV3.       CPI = EV/AC4.       SPI = EV/PV5.       BAC = Sum total of all the planned values6.       EAC = BAC / CPI7.       EAC = AC + ETC — Initial Estimates are flawed8.       EAC = AC + BAC – EV — Future variance are Atypical9.       EAC = AC + (BAC – EV) / CPI — Future Variance would be typical10.    ETC = EAC – AC11.    % of work complete – EV/ BAC12.    VAC = BAC – EAC13.    Formula for To-Complete Performance Index (TCPI),TCPI = (Work Remaining)/(Budget Remaining)This formula can be interpreted in two ways:If you’re under budgetTCPI = (BAC–EV)/(BAC–AC)If you’re over BudgetTCPI = (BAC–EV)/(EAC–AC) The Inputs, Tools and Techniques and Output of Control Costs process are given below: 
Project Management PlanEarned Value ManagementWork Performance Information
Project Funding RequirementsForecastingCost Forecasts
Work Performance DataTo-Complete Performance Index (TCPI)Change Requests
Organizational Process AssetsPerformance ReviewsProject Management Plan Updates
 Project Management SoftwareProject Documents updates
 Reserve AnalysisOrganizational Process Assets updates

Education Edge is a PMI Authorized Training Partner (ATP #4456). Every course is live and instructor-led, and selected courses carry a 100% pass guarantee or your money back.

Not sure which course?

Ask the people who teach it.

Leave your number and we will call you back. Which certification fits you, when the next class starts, what it costs. That is the whole call.

By submitting, you agree to our Privacy Policy and the processing of your personal data.