PMBOK Chapter 6 β Project Time Management
Processes:
Plan Schedule Management (Planning)
Define Activities (Planning)
Sequence Activities (Planning)
Activity Resource Estimate (Planning)
Activity Duration Estimate (Planning
Develop Schedule (Planning)
Control Schedule (Monitoring and Controlling)
ξξξ
Plan Schedule Management
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule
ξξξ
Define activities
The process of identifying and documenting the specific actions to be performed to produce the project deliverables
ξξξ
Sequence activities
The process of identifying and documenting relationships among the project activities
ξξξ
Estimate activity resources
The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity.
ξξξ
Estimate activity durations
The process of estimating the number of work periods needed to complete individual activities with estimated resources.
ξξξ
Develop schedule
The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.
ξξξ
Control Schedule
The process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.
ξξξ
Schedule model
A representation of the plan for executing the project’s activities including durations, dependencies and other planning information, used to produce project schedules along with other scheduling artifacts.
ξξξ
Schedule management plan
A component of the project management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule.
ξξξ
Schedule baseline
The finalized and approved schedule
ξξξ
Project schedule model development
The scheduling methodology and the scheduling tool to be used in the development of the project schedule mode
ξξξ
Level of accuracy
The acceptable range used in determining realistic activity duration estimates is specified and may include an amount for contingencies
ξξξ
Units of measure
Each unit used in measurements is defined for each of the resources
ξξξ
Organizational procedures links
The WBS provides the framework for the schedule management plan, allowing for consistency with the estimates and resulting schedules
ξξξ
Project schedule model maintenance
The process used to update the status and record progress of the project in the schedule model during the execution of the project is defined.
ξξξ
Control thresholds
Variance thresholds for monitoring schedule performance may be specified to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. Thresholds are typically expressed as percentage deviations from the parameters established in the baseline plan.
ξξξ
Lead
The amount of time whereby a successor activity can be advanced with respect to a predecessor activity
ξξξ
Work package quantity estimates
The types and quantities of resources required for each activity in a work package
ξξξ
Critical chain method
The schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties
ξξξ
Late finish date
The latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project copletion date, and any schedule contraints
ξξξ
Program evaluation and review technique (PERT)
The technique for estimating that applies a weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates
ξξξ
Dependency determination
A technique used to identify the type of dependency that is used to create the logical relationships between predecessor and successor activities
ξξξ
Effort
The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks
ξξξ
Summary activity or hammock activity
A group of related schedule activities aggregated and displayed as a single activity
ξξξ
Optimistic duration
An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance
ξξξ
Parametric estimating
The estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters
ξξξ
Activity code
One or more numerical or text values that identify characteristics of the work or in some way categorize the schedule activity that allows filtering and ordering of activities within reports
ξξξ
Activity attributes
A documented tabulation of schedule activities that shows the activity description, activity identifier and a sufficiently detailed scope of work description so project team members understand what work is to be performed
ξξξ
Gantt chart
A bar chart of schedule information where activities are listed on the vertical axis dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates
ξξξ
Late start date
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the project completion date, and any schedule constraints
ξξξ
Network logic
The collection of schedule activity dependencies that makes up a project network diagram
ξξξ
Total float
The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint
ξξξ
Work period
A distinct, scheduled portion work performed during the course of a project
ξξξ
Free float
The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating schedule constraint
ξξξ
Actual duration
The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete
ξξξ
Project schedule network diagram
A graphical representation of the logical relationships among the project schedule activities
ξξξ
Subnetwork
A subdivision (fragment) of a project schedule network diagram, usually representing a subproject or a work package that is often used to illustrate or study some potential or proposed schedule condition such as changes in preferential schedule logic or project scope
ξξξ
Alternatives analysis
A technique used to evaluate identified options in order to select which options or approaches to use to execute and perform the work of the project
ξξξ
Resource histogram
A bar chart showing the amount of time that a resource is scheduled to work over a series of time periods. Resource availability may be depicted as a line for comparison purposes. Contrasting bars may show actual amounts of resources used as the project progresses
ξξξ
Optimistic
An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance
ξξξ
Crashing
The technique used to shorten the schedule duration for the least incremental cost by adding resources
ξξξ
Critical path
The sequence of activities that represents the longest path through a project, which determines the shortest possible duration
ξξξ
Critical path method
The method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model
ξξξ
Forward pass
The critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time
ξξξ
Resource leveling
The technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply. It can cause the original critical path to change, usually to increase.
ξξξ
Apportioned effort
An activity where effort is allotted proportionally across certain discrete efforts and not divisible into discrete efforts.
ξξξ
Precedence diagramming method
A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the
sequence in which the activities are to be performed.
sequence in which the activities are to be performed.
ξξξ
Bottom-up estimating
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS.
ξξξ
Three-point estimating
A technique used to estimate cost or duration by applying an average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.
ξξξ
Schedule network analysis
The technique of identifying early and late start dates, as well as early and late finish dates, for the uncompleted portions of project schedule activities.
ξξξ
Resource optimization techniques
A technique that is used to adjust the start and finish dates of activities that adjust planned resource use to be equal to or less than resource availability
ξξξ
Modeling techniques
What-if scenario analysis and Simulation
ξξξ
Schedule compression
Techniques used to shorten the schedule duration without reducing the project scope, in order to meet schedule constraints, imposed dates, or other schedule objectives.
ξξξ
Fast tracking
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
ξξξ
Earned value management
Schedule performance measurements such as schedule
variance (SV) and schedule performance index (SPI), are used to assess the magnitude of variation to the
original schedule baseline.
variance (SV) and schedule performance index (SPI), are used to assess the magnitude of variation to the
original schedule baseline.
ξξξ
Trend analysis
An analytical technique that uses mathematical models to forecast future outcomes based on historical results. It is a variance from baseline of a budget, cost, schedule, or scope parameter by using prior progress reporting periods’ data and projecting how much that parameter’s variance from baseline might be at some future point in the project if no changes are made in executing the project
ξξξ
Reserve analysis
The technique which incorporates additional time into the schedule activities in recognition of schedule risk
ξξξ
Project buffers
Protects the target finish date from slippage along the critical chain
ξξξ
Feeding buffer
Protect the critical chain from spice along the feeding chain.
ξξξ
Resource smoothing
A technique that adjusts the activities of a schedule model much that the requirements for resources on the project do not exceed certain predefined resource limits. The project’s critical path is not changed and the completion date may not change.
ξξξ
Monte Carlo simulation
Monte Carlo Analysis refers to a technique in project management where a manager computes and calculates the total project cost and the project schedule many times.
ξξξ
Define Activities EEFs
1. Organizational cultures and structure
2. Published commercial information from commercial databases
3. Project management information system (PMIS)
2. Published commercial information from commercial databases
3. Project management information system (PMIS)
ξξξ
Define Activities OPAs
1. Lessons learned knowledge base containing historical information regarding activity lists used by previous similar projects
2. Standardized processes
3. Template that contain a standard activity its or a portion of an activity list from a previous project
4. Existing formal and informal activity planning-related policies, procedures, and guidelines, such as the scheduling methodology, that are considered in developing the activity definitions
2. Standardized processes
3. Template that contain a standard activity its or a portion of an activity list from a previous project
4. Existing formal and informal activity planning-related policies, procedures, and guidelines, such as the scheduling methodology, that are considered in developing the activity definitions
ξξξ
Project documents (updates)
Documents that may influence work and should be monitored within the context of a system for updates