The major output of Project Time Management’s Sequence Activities process is a Network Diagram. So what is a Network Diagram? The function is described in your PMP Exam prep as “visualizing project tasks in boxes with activity IDs and demonstrating the interrelationship between arrow activities.” Network diagrams say how an activity starts with another activity before, after, or at the same time.